Where should an off-specification be recorded?

  • A. Risk Register
  • B. Issue Register
  • C. Work Package
  • D. Configuration Management Strategy


Answer : B

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

  • A. End Stage Report
  • B. Team Plan
  • C. Work Package
  • D. Project Plan


Answer : D

Which is a benefit of using PRINCE2?

  • A. Provides a defined structure of accountability, delegation, authority and communication
  • B. Includes techniques for critical path analysis and earned value analysis
  • C. Enables a Project Manager to be accountable for the success of a project
  • D. Prevents any changes once the scope of a project has been agreed


Answer : A

Which statement is FALSE?

  • A. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
  • B. A project's output is any of the project's specialist products
  • C. A project benefit is only realized after the project has closed
  • D. A project outcome is the result of the change derived from using the project's outputs


Answer : C

Which is a responsibility of the managing level within the project management team?

  • A. Set project tolerances
  • B. Approve stage completion
  • C. Ensure that the products are produced within the constraints agreed with the Project Board
  • D. Appoint the project management team


Answer : C

Which of the following statements about stakeholders are true?
1. Someone who thinks they will be affected by a project is a stakeholder on that project
2. Stakeholders may be internal or external to the corporate organization

  • A. Only 1 is true
  • B. Only 2 is true
  • C. Both 1 and 2 are true
  • D. Neither 1 or 2 are true


Answer : C

Which is a purpose of quality planning?

  • A. Define the structure of the project management team
  • B. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
  • C. Document approval records for those project products that have met their quality criteria
  • D. Produce the Project Plan with resource and schedule information


Answer : B

Identify the missing word in the following sentence. The purpose of the [?] theme is to identify, assess and control uncertainty.

  • A. Change
  • B. Plans
  • C. Quality
  • D. Risk


Answer : D

Which product identifies the management stages and timescales of a project?

  • A. Project Brief
  • B. Project Product Description
  • C. Project Plan
  • D. Initiation Stage Plan


Answer : C

How should the Team Manager report that tolerances are forecast to be exceeded?

  • A. Create an Exception Report
  • B. Create a Highlight Report
  • C. Raise an issue
  • D. Grant a concession


Answer : C

Which is a purpose of a Project Product Description?

  • A. Records the costs and timescales for delivery of the project's final product
  • B. Shows the dependencies between the project's products to aid planning
  • C. Provides a list of all the products to be delivered by the project
  • D. Defines what the project must deliver in order to gain acceptance


Answer : D

Which is a purpose of a Product Description?

  • A. Provide the cost tolerance available for individual products
  • B. Define reporting frequency
  • C. Record the quality checks completed for the End Stage Report
  • D. Document the level of quality required of a product


Answer : D

Which is a purpose of the Business Case theme?

  • A. Identify which role is responsible for producing the Business Case
  • B. Identify the project's outputs
  • C. Establish the controls to manage changes that may impact the project benefits
  • D. Establish a viable investment proposition


Answer : D

Who is the key project decision-maker in the project management team?

  • A. Corporate management
  • B. Executive
  • C. Change Authority
  • D. Project Manager


Answer : B

Which is a purpose of a Project Brief?

  • A. Capture lessons from previous projects
  • B. Ensure that there is a common understanding of the starting point for the project
  • C. Confirm that the Project Plan is able to deliver the Business Case
  • D. Define the quality techniques and standards to be applied during the project