Certified Scrum Master v1.0

Page:    1 / 4   
Exam contains 50 questions

Whose responsibility is it to lead and coach the organization in its Scrum adoption?

  • A. Customer
  • B. Product Owner
  • C. Developers
  • D. Scrum Master


Answer : D

As a true leader the Scrum Master serves:

  • A. the Scrum Team only.
  • B. the management.
  • C. no one.
  • D. the Scrum Team and the larger organization.


Answer : D

Which Agile principle is being practiced if a team chooses to focus on the highest priority product backlog items?

  • A. At regular intervals, the team reflects on how to become more effective, then tunes and adjusts its behavior accordingly.
  • B. Simplicity - The art of maximizing the amount of work not done is essential.
  • C. Business people and developers must work together daily throughout the project.
  • D. The most efficient and effective method of conveying information to and within a development team is face-to-face conversation


Answer : B

Which of the Scrum Values is most demonstrated when a Team completes a task before moving on to the next one?

  • A. Commitment
  • B. Focus
  • C. Respect
  • D. Courage


Answer : B

A developer identified a major technical issue during a Daily Scrum. What should the team do?

  • A. Meet and discuss outside of Daily Scrum
  • B. Interrupt the Daily Scrum and solve the problem immediately
  • C. Escalate it to the Product Owner
  • D. Discuss it during the Sprint Review


Answer : A

Product Backlog refinement is:

  • A. a recurring event in the middle of each Sprint.
  • B. the act of breaking down and further defining Product Backlog items.
  • C. an opportunity for the Developers to estimate Product Backlog items.
  • D. a pre-planning meeting to shorten the length of Sprint Planning.


Answer : B

How should Scrum teams plan work to be performed within Sprints?

  • A. One release at a time, adjusting the number of Sprints to the prior releases' average velocity
  • B. One Sprint at a time, adapting each Sprint Backlog according to what was learned from the last Sprint
  • C. One project at a time, adjusting each Sprint Backlog Item to meet the release date negotiated at inception
  • D. One Sprint at a time in the Product Backlog Refinement meeting with participation of stakeholders


Answer : B

Who makes the final decision on ordering the Product Backlog?

  • A. Lead Developer
  • B. Scrum Master
  • C. Product Owner
  • D. Developers


Answer : C

Which one is true for Sprint Planning?

  • A. The work to be performed in the Sprint is planned
  • B. Demo of the previous increment is done
  • C. Customers will share the feedback
  • D. The Product Backlog is refined


Answer : A

A lightweight framework that helps people, teams and organizations generate value through adaptive solutions for complex problems is known as:

  • A. Kanban.
  • B. Scrum.
  • C. Agile.
  • D. Waterfall.


Answer : B

Which of the following is an activity of Product Backlog management?

  • A. Clearly expressing Product Backlog items
  • B. Creating Sprint tasks
  • C. Facilitating the Daily Scrum
  • D. Planning the Sprint Backlog


Answer : A

When is a Sprint Retrospective meeting held?

  • A. After the Sprint Review and prior to the next Sprint Planning
  • B. At the beginning of the Sprint
  • C. In the middle of the Sprint
  • D. At the end of all the Sprints


Answer : A

Which activity seeks to build consensus in a group setting?

  • A. Coaching
  • B. Teaching
  • C. Mentoring
  • D. Facilitating


Answer : D

Who should the Scrum Master work with to determine if artifacts are completely transparent?

  • A. End users
  • B. Scrum Team and other involved parties
  • C. Management team
  • D. Project Manager


Answer : B

A Scrum Team with all the skills necessary to deliver a usable Increment is:

  • A. divided into sub-teams.
  • B. distributed.
  • C. cross-functional.
  • D. difficult to manage.


Answer : C

Page:    1 / 4   
Exam contains 50 questions

Talk to us!


Have any questions or issues ? Please dont hesitate to contact us

Certlibrary.com is owned by MBS Tech Limited: Room 1905 Nam Wo Hong Building, 148 Wing Lok Street, Sheung Wan, Hong Kong. Company registration number: 2310926
Certlibrary doesn't offer Real Microsoft Exam Questions. Certlibrary Materials do not contain actual questions and answers from Cisco's Certification Exams.
CFA Institute does not endorse, promote or warrant the accuracy or quality of Certlibrary. CFA® and Chartered Financial Analyst® are registered trademarks owned by CFA Institute.
Terms & Conditions | Privacy Policy