Total 80 questions Expand All

Which of the following functions are available in SAP ECC when using capacity leveling?
(Choose three)

  • A. Finite capacity scheduling
  • B. Setup time reduction
  • C. Midpoint scheduling
  • D. Lot size optimization
  • E. Batch size optimization


Answer : A,B,C

Which of the following scheduling types can only be used within capacity planning?

  • A. Forwards
  • B. Only capacity requirements
  • C. Backwards
  • D. Midpoint


Answer : D

An enterprise based in the US produces an end product that is used with the unit of measure "pound" (LB). The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit "kilogram" (KG).
What is the easiest way to fulfill this requirement?

  • A. Create a new material with a reference to the original material and assign the metric unit of measure to the new material master.
  • B. There is no need to take any action. In this scenario, the conversion of units of measurements is done automatically.
  • C. Define a unit of measure group that converts pounds to kilograms in the basic data customizing and assign it to the material master on basic data view 1.
  • D. Add a conversion factor for converting pounds to kilograms on basic data view 1 in the material master.


Answer : B

You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50).
When capacity bottlenecks occur, you should be able to use a second sequence on other work centers for operations 30 and 40.
What sequence category do you use to create the second sequence in the system?

  • A. Substitute sequence
  • B. Standard sequence
  • C. Alternative sequence
  • D. Parallel sequence


Answer : C

Where can you define the default storage location for the material component of a production order? (Choose three)

  • A. Material master (component)
  • B. Routing
  • C. Production supply area of a work center
  • D. Production version (product)
  • E. BOM header (product)


Answer : A,C,D

Which of the following statements about the planning functions available in SAP ECC is correct?

  • A. Master production scheduling (MPS) refers to preferred planning of important materials.
  • B. Material requirements planning (MRP) includes automatic capacity leveling.
  • C. Long-term planning (LTP) is a long-term form of forecast planning.
  • D. In demand management (DM) material shortage situations are identified and corresponding receipt elements are created.


Answer : A

Which properties does ECC Master Production Scheduling (MPS) have? (Choose three)

  • A. MPS items can be taken into consideration by a standard MRP run.
  • B. Non-MPS items can be taken into consideration by an MPS run.
  • C. The planning of MPS and Non-MPS items is always carried out in one planning run.
  • D. MPS items can be defined on MRP Area level.
  • E. MPS items can be defined on plant level.


Answer : B,D,E

You want to use the function "Read PP master data" in the production order. However, while calling the function you receive an error message.
What could be the reason?

  • A. Goods movements have been posted.
  • B. Order papers have been printed.
  • C. The material availability check has been performed.
  • D. The production order has been released.


Answer : A

You want to reduce the uncertainty caused by fluctuating requirements for a finished product by using a dynamic safety stock in SAP ECC.
On which specifications is the dynamic safety stock calculation based?

  • A. The average daily demand and the desired days supply
  • B. The static safety stock and the material forecast
  • C. The static safety stock per day and the safety time
  • D. The average daily demand and the safety time


Answer : A

You want to produce a finished product only when it is requested by a customer order in make-to-order production. However, all assemblies need to be procured beforehand.
How can you fulfill these requirements in SAP ECC? (Choose two)

  • A. Use strategy 30 (production by lots) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.
  • B. Use strategy 40 (planning with final assembly) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.
  • C. Use strategy 50 (planning without final assembly) for the finished product and no strategy for all assemblies in the bill of material.
  • D. Use strategy 20 (make-to-order production) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.


Answer : C,D

Which of the following requirements is supported by using process orders?

  • A. Linkage of documents to orders
  • B. Use of reference operation sets
  • C. Use of production/resource tools
  • D. Documentation of the production using an electronic batch record


Answer : D

Which of the following consequences result when a production order is set to Technically
Complete (TECO)? (Choose three)

  • A. Confirmations are no longer permitted.
  • B. Reservations are no longer relevant for material requirements planning.
  • C. The order and its operations receive the system status Locked (LKD).
  • D. Capacity requirements are set to null.
  • E. The order is no longer relevant for material requirements planning.


Answer : B,D,E

What master data do you need for material replenishment using the KANBAN procedure?
(Choose two)

  • A. Production supply area
  • B. Product cost collector
  • C. Rate routing
  • D. Production version
  • E. Control cycle


Answer : A,E

What can you use to organize material staging for production orders? (Choose three)

  • A. Transfer orders
  • B. Logistics Information System (LIS)
  • C. KANBAN
  • D. Material documents
  • E. Pull list


Answer : A,C,E

You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence.
What do you have to consider in this scenario?

  • A. Planned orders that are created by requirements planning are shifted to the end of the planning time fence.
  • B. Requirements planning considers only changes that are relevant for scheduling within the planning time fence.
  • C. The MRP controller cannot create planned orders within the planning time fence.
  • D. Planned orders are created within the planning time fence and automatically firmed by requirements planning.


Answer : A