A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

  • A. Projectized
  • B. Weak matrix
  • C. Functional
  • D. Balanced matrix


Answer : A

A project charter is an output of which Process Group?

  • A. Executing
  • B. Planning
  • C. Initiating
  • D. Closing


Answer : C

Which tool or technique is effective in a project in which the deliverable is not a service or result?

  • A. Inspection
  • B. Variance analysis
  • C. Decomposition
  • D. Product analysis


Answer : D

An element of the project scope statement is:

  • A. Acceptance criteria.
  • B. A stakeholder list.
  • C. A summary budget,
  • D. High-level risks.


Answer : A

Which document describes the necessary information to determine if a project is worth the required investment?

  • A. Cost baseline
  • B. Service level agreement
  • C. Memorandum of understanding
  • D. Business case


Answer : D

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

  • A. Estimate Costs
  • B. Control Costs
  • C. Determine Budget
  • D. Plan Cost Management


Answer : B

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

  • A. Project team
  • B. Focus group
  • C. Change control board
  • D. Project stakeholders


Answer : C

Plan Schedule Management is a process in which Knowledge Area?

  • A. Project Scope Management
  • B. Project Human Resource Management
  • C. Project Integration Management
  • D. Project Time Management


Answer : D

An output of the Validate Scope process is:

  • A. A requirements traceability matrix.
  • B. The scope management plan.
  • C. Work performance reports.
  • D. Change requests.


Answer : D

The Perform Integrated Change Control process occurs in which Process Group?

  • A. Initiating
  • B. Executing
  • C. Monitoring and Controlling
  • D. Planning


Answer : C

Which input to the Plan Risk Management process provides information on high-level risks?

  • A. Project charter
  • B. Enterprise environmental factors
  • C. Stakeholder register
  • D. Organizational process assets


Answer : A

Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

  • A. Work performance data
  • B. Project documents
  • C. Scope baseline
  • D. Requirements documentation


Answer : B

Change requests are processed for review and disposition according to which process?

  • A. Control Quality
  • B. Control Scope
  • C. Monitor and Control Project Work
  • D. Perform Integrated Change Control


Answer : D

The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

  • A. Work performance information.
  • B. Inspections and audits.
  • C. Payment systems.
  • D. Procurement performance reviews.


Answer : D

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

  • A. Project Communications Management
  • B. Project Integration Management
  • C. Project Risk Management
  • D. Project Scope Management


Answer : B