CPIM - Basics of Supply Chain Management v6.0

Page:    1 / 11   
Exam contains 155 questions

Having the needed materials within easy reach of a subassembly process eliminates waste of:

  • A. motion.
  • B. transportation.
  • C. making defects.
  • D. stocks.


Answer : A

After a quality improvement program has been successfully implemented, the greatest cost of controlling quality typically is the cost of:

  • A. failure.
  • B. appraisal.
  • C. prevention.
  • D. inspection.


Answer : C

An electronic board that provides visibility on the production floor is:

  • A. andon.
  • B. anova.
  • C. ANSI.
  • D. alpha factor.


Answer : A

A production rate based on customer demand is called:

  • A. cycle time.
  • B. takt time.
  • C. lead time.
  • D. queue time.


Answer : B

The principal objective of total quality management in manufacturing is to:

  • A. implement statistical process control.
  • B. meet the expectations of the customer.
  • C. reduce the costs of failure.
  • D. eliminate inspections.


Answer : B

Inventory turns is an appropriate performance measure for which of the following functions?

  • A. Material control
  • B. Activity-based costing control
  • C. Total quality management
  • D. Flexible manufacturing


Answer : A

Which of the following is a graphical representation of a frequency distribution?

  • A. Cause-and-effect diagram
  • B. Pareto analysis
  • C. Scatter diagram
  • D. Histogram


Answer : D

Manufacturing overhead includes which of the following types of costs?

  • A. Interest expense
  • B. Supervision
  • C. Direct labor
  • D. Direct material


Answer : B

The theory of constraints is most effective when:
A. demand environments are unstable.
B. demand environments are stable.
C. the constraint cannot be managed easily.
D. the constraint cannot be identified easily.



Answer : B Topic 2, Demand Management

Which of the following smoothing constants places the most weight on the old forecast?

  • A. 0.4
  • B. 0.3
  • C. 0.2
  • D. 0.1


Answer : D

Which of the following factors most likely will impact the demand for a firm's products or services?

  • A. Forecast accuracy
  • B. Order processing system
  • C. Competition
  • D. Planning horizon


Answer : C

A primary purpose of Quality Function Deployment is to:

  • A. calculate performance limits.
  • B. determine marketing strategies.
  • C. direct product design.
  • D. set pass/fail criteria.


Answer : C

A distributor provides customer service by improving which of the following market driven factors?

  • A. Availability
  • B. Design
  • C. Shelf life
  • D. Quality


Answer : A

When demand is uncertain, what is the most appropriate action to take?

  • A. Recalculate safety stock
  • B. Increase order quantity
  • C. Change method of transportation
  • D. Increase number of warehouses for distribution


Answer : A

Which of the following items is a source of independent demand?

  • A. Customer orders for finished products
  • B. Subassembly requirements from material requirements planning
  • C. Raw material requirements from material requirements planning
  • D. Protective packaging for shipping customer orders


Answer : A